Eight steps to prepare a National Building Renovation Plan
Eight steps to prepare a National Building Renovation Plan
Drawing on five case studies, GreenRenoV8 shows how national teams can build on existing renovation strategies and link building stock data, targets, measures and financing in their final plans.
Authors
Gašper Stegnar, Jožef Stefan Institute, Energy Efficiency Centre, Slovenia
Giovanna Cassavia, Graz University of Technology, Austria
Tajda Potrč Obrecht, Graz University of Technology, Austria
(Note: Opinions in the articles are of the authors only and do not necessarily reflect the opinion of the European Union)
Introduction
By 31 December 2026, each Member State must submit its final National Building Renovation Plan (NBRP) under the recast Energy Performance of Buildings Directive (EPBD). The NBRPs will replace the Long-Term Renovation Strategies (LTRSs) submitted in 2020 as the principal national roadmap for building renovation. They set out how each country will meet its EPBD obligations and achieve a highly energy-efficient, decarbonised building stock by 2050.
Whereas LTRSs were mainly strategic frameworks for mobilising investments and policy actions, NBRPs are more prescriptive and implementation-oriented, linked to renovation trajectories, targets, measures, financing and EU-level monitoring.
They must also follow the harmonised template of Annex II of the Directive, which is intended to make national targets, measures, investment needs and progress comparable across the EU.
The first draft NBRPs, submitted alongside the National Energy and Climate Plans (NECPs), were assessed by the European Commission’s Joint Research Centre (JRC) in July 2026 (Maduta et al., 2026). They had encouraging climate ambitions but significant weaknesses in substance: mandatory indicators were omitted, proposed measures lacked quantified objectives, and investment needs and funding sources were not identified.
An earlier study conducted as part of the LIFE Clean Energy Transition project GreenRenoV8 shows results consistent with those from the JRC’s own assessment (Cassavia et al., 2026). Partners in Austria, Flanders (Belgium), Greece, Slovenia and Spain benchmarked existing strategies and early NBRP drafts against every mandatory Annex II item using a simple checklist. The project then turned this evidence, together with the JRC findings, into a step-by-step guideline for preparing NBRPs. This article presents the checklist and the project’s eight-step method for preparing the final plans. A recent BUILD UP technical article by Joint Research Centre researchers examines the findings from the first 16 complete draft plans.
What changed between the strategy and the plan
The EPBD revision of 2018 required LTRSs but offered only an optional template, and strategies that did not follow it were more likely to contain weaknesses. The 2024 recast responds by replacing LTRSs with mandatory NBRPs. These plans must be prepared using the harmonised template set out in Annex II of the EPBD recast.
The template has seven sections: (A) an overview of the national building stock; (B) a roadmap with targets for 2030, 2040 and 2050; (C) implemented and planned policies and measures; (D) investment needs and financing sources; (E) zero-emission building (ZEB) thresholds; (F) minimum energy performance standards (MEPS) for non-residential buildings; and (G) a national trajectory for the progressive renovation of the residential building stock.
The shift is not merely administrative: NBRPs require a more data-driven, implementation-oriented approach. They call for more granular building-stock information, measurable targets, clearer identification of the worst-performing buildings, more detailed renovation-rate data, explicit financing and investment needs, and links to new EPBD requirements such as ZEB thresholds and MEPS.
A checklist that makes the gaps visible
To show which information is missing from existing strategies when preparing NBRPs, GreenRenoV8 developed a checklist derived directly from the mandatory template of Annex II.
Each mandatory reporting item is classified as ‘adequate’, ‘incomplete’ or ‘missing’, depending on whether the required information is provided. A strategy considered adequate in 2020 may therefore appear incomplete against the more detailed 2024 template. The assessment measures reporting completeness, not the quality or effectiveness of the underlying policies.
The checklist first looks backwards, assessing existing LTRSs against the new NBRP requirements. This shows what can be carried forward and what must be added. The same criteria are then applied to the corresponding draft NBRP, where available. Plotting both side by side reveals whether earlier gaps are being closed.
Assessment material differed between the five case studies: some used draft NBRPs, others updated LTRSs or internal material. For Spain, only the LTRS could be assessed. The results therefore capture different stages of the transition, not five completed plans.
Figure 1 shows the Slovenian results; those for the other case studies are available in Cassavia et al. (2026). Each vertical line represents one mandatory Annex II item, labelled by section letter and sub-item number.
Circles show the LTRS and diamonds the emerging NBRP, positioned in the ‘adequate’, ‘incomplete’ or ‘missing’ background zones.

Figure 1. Checklist-based evaluation of Slovenia’s LTRS (circles) and emerging NBRP (diamonds). Each vertical line is a mandatory Annex II item; colours mark sections A (blue), B (green), C (purple), D (orange), E (yellow), F (pink) and G (red). The dashed line in the ‘adequate’ zone indicates ideal compliance. Adapted from: Cassavia et al. (2026), IOP Conf. Ser.: Earth Environ. Sci. 1615, 012055, CC BY 4.0.
Three patterns emerged across the case studies. First, items assessed as adequate in an LTRS are often missing under the NBRP framework. This reflects new, more detailed requirements rather than weaker planning. In Slovenia (Figure 1), several section C criteria (policies and measures, purple) were adequate in the LTRS but missing in the emerging NBRP, because descriptive LTRS policies must now become quantified, enforceable measures linked to ZEB standards and investment needs to 2050. Missing items may also reflect work still underway. The checklist thus shows what is available, what needs development and what must still be added.
Second, gaps recur across the case studies: (i) financing mechanisms, (ii) the identification and treatment of worst-performing buildings, (iii) current and target renovation rates by renovation depth, (iv) ZEB thresholds, and (v) provisions for exempted buildings. For example, Greece has a well-established framework and detailed stock data, but lacks requirements introduced after its 2021 LTRS, notably annual renovation rates and ZEB thresholds. Spain’s ERESEE 2020 is similarly detailed, especially on stock characterisation and energy poverty, but still needs greenhouse-gas-based ZEB thresholds, non-residential MEPS, quantified investment needs for 2030–2050, and a 2035 milestone for the residential renovation trajectory.
Third, countries with more comprehensive LTRSs are generally better positioned to develop NBRPs. In the example of Flanders, the revised regional energy and climate plan and the Energiekaart Vlaanderen data platform strengthened stock documentation, resulting in several previously missing items being classified as ‘adequate’. Gaps (ii), (iii) and (v) nevertheless remain.
From identified gaps to a workable renovation plan in eight steps
Identifying gaps is only the first step. The GreenRenoV8 Guidelines for the preparation of a National Renovation Plan offer a step-by-step method, without prescribing policy choices, to help national teams assemble evidence, specify measures and connect targets with financing and monitoring.
The method comprises eight steps (Figure 2). Each distinguishes mandatory from optional information, identifies data sources and methods, provides worked examples and includes quality checks informed by the JRC assessment. The method is also supported by a reporting checklist and ready-to-fill tables.

Figure 2. The eight preparation steps of the GreenRenoV8 guidelines. Steps 1–7 correspond to the seven reporting sections in Annex II of the recast EPBD, while Step 8 establishes monitoring and progress reporting across the plan. Source: GreenRenoV8, Jožef Stefan Institute.
Building consistency across the plan
Before drafting, the guidelines recommend establishing four foundations: clear responsibilities for each section; shared definitions and a documented evidence base; stakeholder consultation and a review of the existing LTRS; and a preparation timetable aligned with NBRP and NECP reporting.
The eight preparation steps connect the different parts of the plan:
- Building-stock overview. Assemble a representative building-archetype matrix, define and quantify the worst-performing stock, and document energy consumption, renovation activity and primary-energy factors. Reuse this evidence in subsequent modelling and costing.
- Renovation roadmap. Model coherent trajectories for energy use, emissions and renovation activity, working backwards from the 2050 objective to establish intermediate milestones.
- Policies and measures. Specify each measure’s quantified objective, budget, funding sources, responsible bodies, implementation period and expected impact. Match measures to the needs identified in the roadmap.
- Investment and financing. Estimate investment needs from the modelled renovation activity, distinguish public and private contributions, and identify the financing gap and instruments needed to address it.
- ZEB thresholds. Specify operational greenhouse-gas and primary-energy thresholds for new and renovated zero-emission buildings and use them consistently in the modelling.
- Non-residential MEPS. Define energy-performance thresholds, the affected building stock, and exemption criteria and their implications.
- Residential trajectory. Express the 2030 and 2035 milestones as numerical values for average primary-energy use, consistent with the stock baseline, roadmap and financing strategy.
- Monitoring. Assign indicator owners, data sources and review dates, retain consistent definitions across reporting cycles, and establish a process for adjusting measures when milestones are missed.
In this sequence, missing indicators become explicit data tasks; undefined worst-performing buildings become identifiable target groups; qualitative measures become assessable interventions; and aggregate investment figures become the basis for a financing strategy. The objective is not simply to complete each section, but to demonstrate that the stock data, targets, measures and resources are mutually consistent.
The guidelines also explain why a roadmap cannot rely on renovation-rate targets alone. Figure 3 distinguishes three interacting levers: renovation rate (floor area treated each year), renovation depth (performance achieved) and the shift from fossil-fuel heating to lower-carbon energy carriers. Scenario modelling examines their combined effects rather than treating them as independent targets.

Figure 3. Three interacting levers of building-stock decarbonisation: renovation rate, renovation depth and the transition to lower-carbon energy carriers. Source: GreenRenoV8, Jožef Stefan Institute.
According to the Slovenian default scenario, approximately 84% of the stock becomes zero-emission-ready by 2050, with reductions relative to 2025 of around 30% in final energy, 24% in primary energy and 30% in operational CO₂ emissions. Of the remaining 16%, 7% needs further upgrades and 9% is structurally constrained or cannot be renovated.
Results differ by category: single-family and multi-family buildings reach approximately 89% and 87% zero-emission-ready shares, respectively, compared with 72% for public buildings and 64% for service buildings, indicating where more targeted measures are needed. In the modelling, a 1 % annual renovation rate delivered as deep renovation produces a higher zero-emission-ready share by 2050 than a 2 % rate delivered as partial renovation: depth, not rate alone, determine whether the targets are met, so depth targets need to be set explicitly alongside rate targets. Assumptions on electricity and district-heating decarbonisation must also align with the NECP, as emission reductions depend on energy supply as well as renovation.
Beyond the regulatory minimum
The guidelines supplement the reporting framework given in Annex II of the EPBD with four important additions developed in the GreenRenoV8 project, namely:
(i) whole-life-carbon assessment,
(ii) combined energy and seismic renovation,
(iii) financing toolbox, and
(iv) building-stock scenario modelling.
(i) Whole-life-carbon assessment makes embodied emissions and operational savings visible together (ii) In seismic regions, combined energy and structural interventions address decarbonisation and safety together. (iii) The financing toolbox (feasibility assessment, financing navigator and timeline) supports the selection and sequencing of instruments. (iv) Building-stock scenario modelling links the current stock to the 2050 objective. Using building archetypes, it tests combinations of the three levers described above.
Together, these methods support an NBRP that explains not only its targets but also the interventions, resources and monitoring needed to reach them.
Conclusions
The transition from LTRSs to NBRPs requires more than a new reporting format: Member States must connect building-stock information, measurable targets, policy measures and financing within a coherent implementation framework. The GreenRenoV8 checklist and the JRC assessment indicate that existing strategies provide useful foundations, but recurring gaps remain in data completeness, the identification of worst-performing buildings, policy quantification and the connection between investment needs and funding sources.
The GreenRenoV8 guidelines address these gaps by bringing the sections of the plan together, using consistent evidence to develop trajectories, specify measures, estimate costs and monitor progress. This approach is supported by scenario modelling, whole-life-carbon assessment, seismic considerations and financing tools.
However, reporting completeness should not be confused with implementation capacity or policy effectiveness. The checklist assesses whether information is present, while modelling results remain conditional on the underlying data and assumptions.
For the final NBRPs, the priority is to move from stated ambition to transparent and assessable commitments: clearly defined target groups, quantified measures, identifiable financing arrangements and monitoring responsibilities. A complete template is an important starting point, but the plans’ value will ultimately depend on whether these commitments translate into renovation activity and measurable progress towards the 2050 objective.