Sisk retrofits its headquarters to reduce energy demand
Sisk retrofits its headquarters to reduce energy demand
The retrofit of Sisk's Dublin headquarters achieves modelled energy and cost savings of 49.92% against the ASHRAE 90.1-2010 baseline, with improvements in HVAC, lighting and domestic hot water.
Sisk's Dublin headquarters has undergone a building renovation to improve its energy performance and meet Leadership in Energy and Environmental Design (LEED) v4 requirements. The three-storey commercial building, with 3,241 m² of serviced floor area, incorporates upgraded heating, ventilation and air conditioning (HVAC) systems and accommodates offices, a coffee shop, workshop and gym. IES Consulting used IES Virtual Environment (IESVE) to model its energy performance during the design and tender stages.
The proposed model was compared with baseline models generated in accordance with ASHRAE 90.1-2010. According to the simulation, the retrofit achieves total energy and cost savings of 49.92% compared with the baseline scenario, equivalent to 25 optimised energy performance points under LEED Interior Design and Construction (ID+C).
The modelled results include energy savings of 33.8% for interior lighting and 82.4% for space cooling, alongside heating cost savings of 59.8%. Energy consumption for interior fans falls by 19.3%, while domestic hot water achieves energy savings of 81.6% through low-flow fixtures. The modelling also enabled the HVAC systems to be assessed and compliance with LEED v4 requirements to be documented.
Key figures:
- Building condition: Renovated existing building
- Building type: Three-storey commercial office building
- Delivery year: The publication date of the case study is 2 September 2026, but the building delivery/completion year is not stated.
- Certification target: LEED v4
- Energy cost savings: 49.92% compared with the ASHRAE 90.1-2010 baseline
- LEED score: 25 Optimised Energy Performance points